Timeline
14 of 27 complete · 2 late, 1 of them on the critical path.
Critical path
Ordered by what a slip actually delaysData room final
Due Aug 1, 2026 · nothing depends on it
Buyer research baselines
Due Feb 1, 2026 · nothing depends on it
Data room audit
Due Feb 1, 2026 · nothing depends on it
Exit readiness assessment
Due Feb 1, 2026 · nothing depends on it
Financial reporting foundation
Due Mar 1, 2026 · nothing depends on it
Relationship development
Due Apr 1, 2026 · nothing depends on it
Enterprise dealer group wins
Due Jun 1, 2026 · nothing depends on it
Quiet strategic conversations
Due Jun 1, 2026 · nothing depends on it
Metric improvement
Due Aug 1, 2026 · nothing depends on it
Top buyer engagement
Due Aug 1, 2026 · nothing depends on it
Management presentation ready
Due Aug 1, 2026 · nothing depends on it
NDAs executed
Due Sep 1, 2026 · nothing depends on it
Formal process launch
Due Oct 1, 2026 · nothing depends on it
Management meetings
Due Oct 1, 2026 · nothing depends on it
Diligence round one
Due Oct 1, 2026 · nothing depends on it
IOIs received
Due Oct 1, 2026 · nothing depends on it
LOIs received
Due Nov 1, 2026 · nothing depends on it
Competitive bidding
Due Nov 1, 2026 · nothing depends on it
Buyer selection
Due Nov 1, 2026 · nothing depends on it
Confirmatory diligence
Due Dec 1, 2026 · nothing depends on it
Definitive agreement
Due Dec 1, 2026 · nothing depends on it
Closing
Due Dec 1, 2026 · nothing depends on it
Months 1–2 · Transaction prep
6/6Transaction preparation
Dec 1, 2025 – Feb 1, 2026 · M&A Advisor
◆Buyer research baselines
Dec 1, 2025 – Feb 1, 2026 · The company Founder
◆Data room audit
Dec 1, 2025 – Feb 1, 2026 · The company Founder
◆Exit readiness assessment
Dec 1, 2025 – Feb 1, 2026 · The company Founder
◆Financial reporting foundation
Dec 1, 2025 – Mar 1, 2026 · The company Founder
Internal initiative kickoff
Dec 1, 2025 – Feb 1, 2026 · M&A Advisor
Months 2–4 · Relationship development
3/4◆Relationship development
Feb 1, 2026 – Apr 1, 2026 · The company Founder
◆Enterprise dealer group wins
Feb 1, 2026 – Jun 1, 2026 · The company Founder
◆Metric improvement
Feb 1, 2026 – Aug 1, 2026 · The company Founder
Buyer intelligence monitoring
Feb 1, 2026 – Dec 1, 2026 · M&A Advisor
Months 4–6 · Strategic conversations
2/31 late◆Quiet strategic conversations
Apr 1, 2026 – Jun 1, 2026 · The company Founder
Buyer-specific value creation
Apr 1, 2026 – Aug 1, 2026 · M&A Advisor
Management positioning
Apr 1, 2026 – Aug 1, 2026 · M&A Advisor
Months 6–8 · Buyer engagement
2/31 late◆Top buyer engagement
Jun 1, 2026 – Aug 1, 2026 · The company Founder
◆Data room final
Jun 1, 2026 – Aug 1, 2026 · The company Founder
◆Management presentation ready
Jun 1, 2026 – Aug 1, 2026 · The company Founder
Months 8–10 · Formal process
1/5◆Formal process launch
Aug 1, 2026 – Oct 1, 2026 · The company Founder
◆NDAs executed
Aug 1, 2026 – Sep 1, 2026 · The company Founder
◆Management meetings
Aug 1, 2026 – Oct 1, 2026 · The company Founder
◆Diligence round one
Sep 1, 2026 – Oct 1, 2026 · The company Founder
◆IOIs received
Sep 1, 2026 – Oct 1, 2026 · The company Founder
Months 10–11 · LOI and selection
0/3◆LOIs received
Oct 1, 2026 – Nov 1, 2026 · The company Founder
◆Competitive bidding
Oct 1, 2026 – Nov 1, 2026 · The company Founder
◆Buyer selection
Nov 1, 2026 – Nov 1, 2026 · The company Founder
Months 11–12 · Close
0/3◆Confirmatory diligence
Nov 1, 2026 – Dec 1, 2026 · The company Founder
◆Definitive agreement
Nov 1, 2026 – Dec 1, 2026 · The company Founder
◆Closing
Dec 1, 2026 – Dec 1, 2026 · The company Founder